System 205 Installation Advice
Hook-On Tiles, Concealed Grid
NotesWhere two J-bars meet and are spliced together, a gallows bracket should be installed within 300mm.It is considered good practice to stagger joints in supporting structures. Additional LoadsWhen supporting services such as downlights, speakers, detectors and other mechanical and electrical services, the maximum load applied to the ceiling tile must not exceed 7kg including spreader yokes if applicable.The application of a load should always be considered. Please consult the SAS technical department for further advice. For loading for flange formed reinforced apertures, please consult with the SAS technical department. |
|